Project Milestone Status

Project Milestones Status

Project Milestone Description (Days from Appointed Date) Planned Actual Delay (No. of months) Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 150 20 08.03.2023 20 % 30.04.2023 1.5 Achieved
Project Milestone-II 300 35 05.08.2023 35 % 25.10.2023 2.5 Achieved
Project Milestone-III 540 75 01.04.2024 75 % 31.05.2024 2.0 Achieved
Schedule Completion Date 730 100 08.10.2024       In Progress