Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Status | ||
---|---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
Project Milestone-I | 150 | 20 | 08.03.2023 | 20 % | 30.04.2023 | 1.5 | Achieved |
Project Milestone-II | 300 | 35 | 05.08.2023 | 35 % | 25.10.2023 | 2.5 | Achieved |
Project Milestone-III | 540 | 75 | 01.04.2024 | 75 % | 31.05.2024 | 2.0 | Achieved |
Schedule Completion Date | 730 | 100 | 08.10.2024 | In Progress |